Proxy - Minor Version or Patch Level Upgrade (Y or Z Upgrade)
Before you perform any proxy update, schedule a maintenance window. The clients registered to Uyuni through the proxy will not be able to connect to Uyuni while the update is in progress. For more information about maintenance windows, see administration:maintenance-windows.adoc.
When upgrading Uyuni Proxy 4.0, ignore the option to upgrade it to version 4.1 as target product. Always select to upgrade Uyuni Proxy 4.0 to Uyuni Proxy 4.2 only. |
1. Update the Proxy (Y)
To update a proxy use the Product Migration
:


2. Update the Proxy (Z)
To update a proxy you first stop the proxy service, then update the software and finally restart the proxy service.
-
On the Uyuni Proxy, stop the proxy service:
spacewalk-proxy stop
-
In the Uyuni Server Web UI, navigate to
and click the name of the proxy. -
Select packages to be updated on the proxy, and then apply the selection.
-
On the Uyuni Proxy, start the proxy service:
spacewalk-proxy start
If you need to update many proxies, you can create an action chain of this command sequence on the Uyuni Server. You can use the action chain to perform updates on multiple proxies at the same time.